Opp. Hotel Shaurya, RambhuvanWado, , Ribandar, Goa. , North Goa
RERA Registration No. : PRGO05180253 Registration Type : Company
Date of Registration :
Fri May 11 16:23:27 IST 2018
Total Area of Project Land :
2330.0
Project Type :
Residential/Group Housing
Project Start Date :
16-05-2016
Project End Date :
31-03-2021
Project Status :
Completed
Chalta No.:
P.T. Sheet No:
Total Open Area (Sq Mtr) :
1690.0
Total Covered Area(Sq Mtr) :
640.0
State :
Goa
District:
North Goa
Village:
Estimated Cost of Project:
No. of Garage :
0
Area of Garage :
0.0
No. of Open Parking :
10
Area of Open Parking :
125.0
No. of Covered Parking :
16.0
Area of Covered Parking :
406.0
No. of Covered Parking Sold :
0
No. of Open Parking Sold :
0
Block 2 is having 8 Single & 12 Double bed room flats. There are 2 staircase blocks with 2 lifts. Block 1-A has two double height stories of commercial area which is proposed to be converted to double height ground floor and two standards floors above. There is a garden area and a swimming pool;and club house and gym located in Block 1, which will be used by the occupants of the entire project.
| Type of Promoter | Name | Mobile Number | |
|---|---|---|---|
| Partnership Firm | Vaastu Estate Developers | contact[at]vaastugoa[dot]com | 7720002669 |
| Name | Mobile | Address | |
|---|---|---|---|
| Mr Sunil Morajkar | 9822127899 | vaastuestatedevelopers[at]gmail[dot]com | Near Mundial Palace Hotel, Miramar, North Goa, Goa |
Project Name:
Vaastu Ribandar Foothills Block 1
Project Description:
This project is the first phase of complex named as Vaastu Ribandar Foothills and named as Block 1. It has total of twenty flats, four single bed room and sixteen two bed room. It has a basement, stilt parking and four top stories. The Club house and Gym for Block 1, Block 2 and Block 1-A is located in the stilt area of his block.
Current Status :
Completed
Type of Project:
Residential
Project Completion Certificate:
Is there any case pending:
No
Is Payment Pertaining to Project Land Pending:
No
Project Address:
Opp. Hotel Shaurya, Rambhuvan Wado, Ribandar Goa.
State/UT:
Goa
District:
North Goa
Pin Code:
403006
Project Name:
Vaastu Hanging Gardens
Project Description:
This project has stilt plus three floors with a total of eighteen apartments. It has twelve two bedroom and six three bedroom apartments. Parking for all the apartments is provided in the stilt area.
Current Status :
Completed
Type of Project:
Residential
Project Completion Certificate:
Is there any case pending:
No
Is Payment Pertaining to Project Land Pending:
No
Project Address:
Near Bal Bharati School, Ribandar Goa.
State/UT:
Goa
District:
North Goa
Pin Code:
403006
Project Name:
Vaastu Ribandar Foothills Block 2
Project Description:
This project is an ongoing project and under RERA registration. This project is comprising of 20 apartments, eight of them are single bedroom and twelve of them are double bedroom apartments. The building is having stilt plus four stories with sixteen number of parking slots under the stilts and four open parking spaces.
Current Status :
Ongoing
Type of Project:
Residential
Expected Completion Date:
31-03-2020
Is there any case pending:
No
Is Payment Pertaining to Project Land Pending:
No
Project Address:
Opp. Hotel Shaurya, Rambhuvan Wado, Ribandar, Goa.
State/UT:
Goa
District:
North Goa
Pin Code:
403006
| Type of Inventory | No of Inventory | Carpet Area (Sq Mtr) |
Area of exclusive balcony/verandah (Sq Mtr) |
Area of exclusive open terrace if any (Sq Mtr) |
|---|---|---|---|---|
| Shops | 2 | 235.22 | 0.0 | 54.66 |
| Flats | 9 | 494.11 | 149.51 | 0.0 |
| No Of Inventory Completed |
No Of Inventory Booked |
No Of Inventory Sold |
|---|---|---|
| Architect Name | Address | Pin Code | Year of Establishment | |
|---|---|---|---|---|
| Yatin Pukhraj Jain | yatin[at]mayadesigngoa[dot]co[dot]in | 905, Pundalik Nagar, , Alto Porvorim, Bardez-Goa | 403521 | 2012 |
| Engineer Name | Address | Pin Code | Year of Establishment | |
|---|---|---|---|---|
| Dr Raghuvir K Salkar | salkar[at]ksa-india[dot]com | A-2, Ramakant Apartments, St.Inez | 403001 | 1997 |
| Road System | Water Supply | Sewage and Drainage System | Electricity Supply Transformer And Sub Station | Solid Waste Management And Disposal |
|---|---|---|---|---|
| Self Development % Completed | Government Authority % Completed | Government Authority % Completed | Self Development % Completed | Self Development % Completed |
| Work Description | Work Completion in Percentage |
|---|---|
| Gymkhana % Completed | Government Authority % Completed |
| Swimming Pool % Completed | Government Authority % Completed |
| Landscaping Tree Planting % Completed | Government Authority % Completed |
| Generator % Completed | Government Authority % Completed |
| Street Lighting % Completed | Government Authority % Completed |
| Community Building % Completed | Government Authority % Completed |
| Financial Year | Financial Year Start | Financial Year End | Status Report | Update Date |
|---|---|---|---|---|
| FY2018-2019 | 22-Mar-2018 | 21-Mar-2019 | FORM 6-Annual Report.pdf | 28-Feb-2020 |
| FY2019-2020 | 22-Mar-2019 | 21-Mar-2020 | Statement of Account 2019-20.pdf | 31-Mar-2021 |
| Approval Taken From | Reference No | Date | Updated On |
|---|
| Pending Approvals |
|---|