Last Updated On   

VENKAT MUPPANA
Authorized Person, Laguna Azul Phase 5 (C3 & G)

Laguna Azul Phase 5 (C3 & G)

SANCOALE VILLAGE , MORMUGAO , South Goa

RERA Registration No. : PRGO09221701 Registration Type : Company Registration Certificate

Date of Registration :

Mon Sep 19 13:03:17 IST 2022

Total Area of Project Land :

3350.0

Project Type :

Residential/Group Housing

Project Start Date :

27-06-2022

Project End Date :

31-12-2024

Project Status :

New Project Launch

Chalta No.:

NA

P.T. Sheet No:

NA

Total Open Area (Sq Mtr) :

1669.56

Total Covered Area(Sq Mtr) :

840.44

State :

Goa

District:

South Goa

Village:

Sancoale (ct)

Estimated Cost of Project:

237822820

No. of Garage :

0

Area of Garage :

0.0

No. of Open Parking :

0

Area of Open Parking :

0.0

No. of Covered Parking :

64.0

Area of Covered Parking :

668.2

No. of Covered Parking Sold :

0

No. of Open Parking Sold :

0

Project Funding:

Public Financed

Project Description

RESIDENTIAL / GROUP HOUSING

Promoter Details

Type of Promoter Name E-mail Mobile Number
Company MVR SEAVIEW HOMES PRIVATE LIMITED mvrseaviewhomes[at]gmail[dot]com 8390556776

Authorized Person Details

Name Mobile E-mail Address
VENKAT MUPPANA 8380018679 cre[at]mvrhomesgoa[dot]com Plot No 93, Alto Nagali, Dona Paula, Dona Paula, Panjim, North Goa, Goa

Inventory Details

Type of Inventory No of Inventory Carpet Area
(Sq Mtr)
Area of exclusive balcony/verandah
(Sq Mtr)
Area of exclusive open terrace if any
(Sq Mtr)
Flats 64 5041.6 1347.2 0.0

Quarterly status of the project

No Of Inventory Completed
No Of Inventory Booked
No Of Inventory Sold
0 16 16

Associated Vendor


Project Architects

Architect Name Email Address Pin Code Year of Establishment
Soares and Associates SOARES88[at]GMAIL[dot]COM G-1, VIKAS BUILDING,, 18TH JUNE ROAD, PANAJI 403001 2010

Structural Engineers

Engineer Name Email Address Pin Code Year of Establishment
PARESH GAITONDE pareshg28[at]yahoo[dot]com BT-5 and bt-7, campal,,, Panaji 403001 2010

External Development Work

Road System Water Supply Sewage and Drainage System Electricity Supply Transformer And Sub Station Solid Waste Management And Disposal
Government Authority     % Completed Government Authority     % Completed Self Development      % Completed Government Authority      % Completed Self Development      % Completed
Financial Year Financial Year Start Financial Year End Status Report Update Date

Approval Taken From Reference No Date Updated On

Pending Approvals

Building Details

Completion Percentage













Facilities/Amenities

Proposed

Work Done Percent

Details







Please Select Street Lighting Yes/No









Document

Project Documents

Declaration

Photographs