Last Updated On   Tue Aug 26 14:04:33 IST 2025

DAMODAR ALIAS CHIRAG DATTA NAIK
Authorized Person, CD TIMES SQUARE (PHASE-II)

CD TIMES SQUARE (PHASE-II)

CD TIMES SQUARE , GOGOL MARGAO GOA , South Goa

RERA Registration No. : PRGO09201173 Registration Type : Company Registration Certificate

Date of Registration :

Thu Sep 03 16:55:12 IST 2020

Total Area of Project Land :

2922.0

Project Type :

Commercial

Project Start Date :

27-08-2020

Project End Date :

30-06-2024

Project Status :

Completed

Completion Certificate:

Occupancy Certificate:

Chalta No.:

36 AND 37

P.T. Sheet No:

132

Total Open Area (Sq Mtr) :

1598.6

Total Covered Area(Sq Mtr) :

1065.4

State :

Goa

District:

South Goa

Village:

Margao

Estimated Cost of Project:

242944640

No. of Garage :

0

Area of Garage :

0.0

No. of Open Parking :

24

Area of Open Parking :

300.0

No. of Covered Parking :

86.0

Area of Covered Parking :

1932.02

No. of Covered Parking Sold :

0

No. of Open Parking Sold :

0

Project Funding:

Public Financed

Project Description

COMMERCIAL PROJECT CONSISTING OF SHOPS & OFFICES

Promoter Details

Type of Promoter Name E-mail Mobile Number
Company COMMONWEALTH DEVELOPERS PVT LTD kdnaik[at]cdhomes[dot]com 9552564616

Authorized Person Details

Name Mobile E-mail Address
DAMODAR ALIAS CHIRAG DATTA NAIK 9552564616 kdnaik[at]cdhomes[dot]com COMBA, MARGAO SALCETE , South Goa, Goa

Inventory Details

Type of Inventory No of Inventory Carpet Area
(Sq Mtr)
Area of exclusive balcony/verandah
(Sq Mtr)
Area of exclusive open terrace if any
(Sq Mtr)
Shops 84 4839.43 811.26 301.65

Quarterly status of the project

No Of Inventory Completed
No Of Inventory Booked
No Of Inventory Sold
0 35 0

Associated Vendor


Project Architects

Architect Name Email Address Pin Code Year of Establishment
RAJEEV M SUKHTHANKER archrajsuk[at]gmail[dot]com F1 FIRST FLOOR FATIMA CHAMBERS, NEAR FATIMA CONVENT MARGAO GOA 403601 1990

Structural Engineers

Engineer Name Email Address Pin Code Year of Establishment
OLAVO CARVALHO carvalho[dot]olav[at]gmail[dot]com 405 FOURTH FLOOR RAGHUNATH ESQUIRE , ABOVE MARIO GALLERY PAJIFOND MARGAO GOA 403601 1990

External Development Work

Road System Water Supply Sewage and Drainage System Electricity Supply Transformer And Sub Station Solid Waste Management And Disposal
Government Authority     100% Completed Government Authority     100% Completed Government Authority      100% Completed Government Authority      100% Completed Government Authority      100% Completed
Financial Year Financial Year Start Financial Year End Status Report Update Date
FY2020-2021 27-Aug-2020 26-Aug-2021 CD times square sign.pdf 21-May-2022
FY2021-2022 27-Aug-2021 26-Aug-2022 Audit report 21-22 CD Times Square.pdf 20-Dec-2022
FY2022-2023 27-Aug-2022 26-Aug-2023 Time Square- RERA Audit Report 22-23.pdf 18-Dec-2023
FY2023-2024 27-Aug-2023 26-Aug-2024 RA-Time Square_23-24.pdf 07-Dec-2024

Approval Taken From Reference No Date Updated On

Pending Approvals

Building Details

Completion Percentage













Facilities/Amenities

Proposed

Work Done Percent

Details







Please Select Street Lighting Yes/No









Document

Project Documents

Additional project related documents/ information

Type Caption Document
Other documents/information Architect Certificate Architect Certificate.pdf

Declaration

Photographs